employer cover photo
employer logo
employer logo

Defence Construction Canada/Construction de Défense Canada

Empleador activo

Pregunta de entrevista de Defence Construction Canada/Construction de Défense Canada

Describe the change order process.

Respuesta de la entrevista

Anónimo

11 feb 2019

When contract documents don't provide enough or the correct information, the contractor will send an RFI to the consultant. If there needs to be a change to the design, it is issued in a CCN. Once the work is priced, the contractor will submit a quote to the owner/consultant, if approved, a change order is issued and the work proceeds as per the CCN.

5